Split Supplier Deliveries: 80 Seals Can Start a 100-Pump Order

An order needs 200 seals for 100 pumps. Eighty seals arrive Monday and 120 Wednesday. Building 40 complete kits first meets Wednesday's deadline with one extra setup.

Isometric illustration for Split Supplier Deliveries: 80 Seals Can Start a 100-Pump Order

A 100-pump order needs 200 seals. The supplier will release 80 seals to your warehouse on Monday and the remaining 120 on Wednesday. Waiting for all 200 pushes assembly into Thursday. Starting with 40 complete kits finishes the order on Wednesday, at the cost of one additional setup.

Split supplier deliveries provide a purchased quantity in more than one receipt. For production planning, each usable receipt supports a specific quantity of complete assemblies. The total purchase-order quantity does not establish what can start today.

Convert each receipt into complete pump kits

Each pump needs 2 seals. All other components for the 100 pumps are available and released. There are no other orders competing for these seals.

The supplier's two deliveries become usable after receiving and inspection:

  • Monday at 09:00: 80 seals.
  • Wednesday at 09:00: 120 seals.

Those are available-to-use times, not truck-arrival estimates. The same two receipts and inspections occur whether assembly starts Monday or waits until Wednesday.

Monday's complete-kit quantity is:

80 ÷ 2 = 40 pumps.

Wednesday's receipt supports:

120 ÷ 2 = 60 pumps.

Together:

40 + 60 = 100 pumps.

Releasing all 100 on Monday would leave 60 incomplete kits. The full-kit rule still applies to every pump released.

Compare two assembly schedules against Wednesday's deadline

The assembly cell operates from 08:00 to 16:00 with continuous staffing. Each pump takes 6 minutes through the scheduled assembly and in-cell check.

The order must complete that operation by Wednesday at 16:00. Packing and dispatch are separate commitments. The cell has the necessary Monday, Wednesday and Thursday capacity, and earlier work will not displace another order.

Each production batch requires a 30-minute setup. It can be completed before the seals are issued, using the approved instructions, tools and other components. The cell is available from 08:30 for that work on both relevant days.

Wait for the full receipt

Complete one setup on Wednesday from 08:30 to 09:00. All 200 seals are then available.

The processing requirement is:

100 × 6 = 600 minutes, or 10 hours.

Wednesday provides 7 processing hours after 09:00:

7 × 60 = 420 minutes.

That produces:

420 ÷ 6 = 70 pumps.

The remaining 30 need:

30 × 6 = 180 minutes, or 3 hours.

They finish Thursday at 11:00. The Wednesday production deadline is missed.

Release two complete production batches

On Monday, set up from 08:30 to 09:00. Build the first 40 pumps:

40 × 6 = 240 minutes, or 4 hours.

They finish at 13:00.

On Wednesday, set up again from 08:30 to 09:00. Build the other 60:

60 × 6 = 360 minutes, or 6 hours.

They finish at 15:00, one hour before the production deadline.

The two batches still contain the same 100 pumps. They use 600 processing minutes plus 60 setup minutes. Waiting uses 600 plus 30. The earlier finish therefore costs 30 additional minutes of cell capacity.

Myth: a partly delivered purchase order means an incomplete production order

A partially received purchase order can support complete units of finished production. The useful question is how many complete kits the received quantity supplies.

In this example, the 80 seals support 40 fully supplied pumps. The planner can keep one customer order while organizing production in two batches. There is no requirement to send the customer two deliveries.

Think of baking for a school event when ingredients arrive in two trips. If the first trip provides everything for four trays, those trays can be completed while the remaining ingredients are on their way. Starting ten half-supplied trays would create a different problem.

Before splitting production, MRP should connect the usable supply to the demand it covers. A second order must not reserve Monday's same 80 seals at the same time.

Include what the earlier finish costs

The first 40 pumps wait as completed output from Monday afternoon until the balance is ready Wednesday. Allow for storage, identification and any required preservation. A customer-specific or revision-sensitive product deserves particular attention during that wait.

Expediting the entire seal quantity would provide another option, but the split plan already meets the stated deadline. Compare any extra freight with a benefit the customer actually needs.

If the Wednesday receipt moves, recalculate the second batch rather than assuming the original purchase-order total protects the date. The distinction between physical stock and available material remains important after every receipt.

In factory.online, MRP links open supply and shortages to manufacturing demand. The planner can compare one assembly batch with two batches in planning scenarios and see the extra setup alongside the earlier completion on the finite-capacity Gantt.